IMPORTANT NOTICE: Zane Highway Paving Update

Posted on: June 25, 2015

Lash Paving has set up a new paving schedule for Zane Highway as of Thursday June 25th. ?

Paving will not?begin on Friday June 26th as planned.

On Saturday June 27th, milling will begin from Aetna Street to Madison Street.

On Monday June 29th, paving will begin from Aetna Street to Madison Avenue.

On Tuesday June 30th and beyond, the milling and paving?will continue north until the project is completed at the Fifth Street Exit.

We apologize for the inconvenience this schedule change may cause, however due to weather these changes must take place. Thank you for your continued patience during this project and soon we will all be enjoying a smooth drive on Zane Highway.